
Doosan Škoda Power Supplies Back-Pressure Turbines for Plock Plant
Key Takeaways
- ORLEN Group's €125 million contract with Doosan Škoda Power includes two 55-MW turbines and a generator for Plock, Poland, with completion by 2029.
- The project will improve efficiency by 9%, reducing costs and environmental impact, while maintaining operations during construction.
The company will execute reconstruction while six installed machines, boilers, and other equipment remain in full operation, presenting a challenge that requires extensive coordination.
The
“This investment is being realized as an EPC contract, which means a turnkey delivery of technology—from the design of the turboset through manufacturing, installation, and commissioning,” said Tomáš Winkler, Head of Project Management Department at Doosan Škoda Power. “The newly supplied turbosets and associated technology will have 9% higher efficiency compared to the original technology, which will significantly contribute to more efficient electricity and heat generation and reduced operating costs as well as environmental footprint.”
Specifically, the order includes two single-casing extraction DST-S10 back-pressure steam turbines and a two-pole generator, with the first turboset component deliveries taking place in early 2025. Doosan will also supply transformers, bus ducts, and install two underground 30-kV high-voltage cable interconnections between the existing and new switch gear. Lastly, the company will execute foundation construction using micropiles.
“The newly supplied units are significantly more complex in terms of layout and redundancy and must be integrated into available existing layout,” said Winkler. “To ensure maximum precision and minimize risks, we utilized 3D-scanning technology, which formed the basis for detailed design preparation.”
Doosan must complete reconstruction while six existing units, boilers, and technological equipment remain in full operation, presenting a significant challenge that requires extensive coordination. The company has been on the Plock construction site for eight months, nearly completing its civil works phase before following phases. TG4 assembly may be fully completed by year-end 2025, with operational handover scheduled for October 2026. In order to maintain continuous and safe operation, the project is divided into two stages:
- Following a six-month break, in which the owner shuts down and disassembles TG5, work will resume
- Doosan begins work on TG5’s second unit, with operational handover scheduled for mid-2029
The contract also includes a 10-year service agreement for each modernized turboset.
LNG Storage Tanks
This week, the Korea Gas Corp. (KOGAS)
Building out the Dangjin LNG storage tank infrastructure falls under the broader LNG Production Base Project at the Dangjin Seokmun National Industrial Complex, which intends to improve South Korea’s LNG supply-demand balance. During Phase 1 in 2021, Doosan Enerbility completed roof air-raising work for four LNG tanks and is currently executing internal construction work.
Doosan & HD Hyundai
In early May 2025,
Newsletter
Power your knowledge with the latest in turbine technology, engineering advances, and energy solutions—subscribe to Turbomachinery International today.





