|Articles|May 31, 2013
New 368MW gas power plant for Algeria
Author(s)TMI Staff & Contributors
Advertisement
In consortium with General Electric, METKA S.A. recently announced the signing of a new contract with Société Algérienne de Production de l’Electricité (SPE Spa), for development of a new gas-fired power plant.
The project concerns the engineering, procurement, construction (EPC) and commissioning of an open cycle gas turbine power plant with two gas turbines and a total output of 368 MW located in Hassi R’mel, Algeria.
The total value of the deal is approximately $120m with a contracted schedule of 29.5 months. This is Greek multinational METKA’s third major project in Algeria.
Advertisement
Advertisement
Advertisement
Trending on Turbomachinery Magazine
1
Hawaiian Electric Orders Six GE Vernova LM6000VELOX Units to Repower Waiau Plant
2
Entergy, MHI Group MOU Targets 50% CCS Cost Reduction with Integrated GTCC Solution
3
Baker Hughes Closes Chart Industries Deal, Adding $4.3B Industrial Segment
4
GE Vernova Expands Niskayuna Research Campus With $110M Investment in Energy Tech
5