At the 2026 Turbomachinery and Pump Symposia, Engro Fertilizers’ Muhammad Uzair Javed explained how his team traced persistent high vibration to train misalignment, then moved a 100-ton turbine skid to cut vibration in half.
Discover the biggest limiting factors behind ramping up LNG production in the latest episode of the TurboTime podcast.
Part two of the TurboTime podcast with Myth Busters Klaus Brun and Rainer Kurz, dives further into the limiting factors involved in the LNG production process. There are various components involved, and each requires gas turbine-driven or electric motor-driven compressors. The pair also address current events involved in gauging and limiting the amount of CO2 released into the atmosphere. Cost, cost, cost is on everybody's mind and is a major hurdle in solving the issue of bolstering LNG production levels.