
Mitsubishi Power Fulfills H-25 Gas Turbine Order for Plant Conversion in Taiwan
Key Takeaways
- Chang Chun Petrochemical's Miaoli Factory will transition to a natural gas-fired cogeneration system with Mitsubishi Power's H-25 gas turbine, enhancing efficiency and reducing emissions.
- Mitsubishi Power's longstanding relationship with Chang Chun is reinforced by the second H-25 unit order, aligning with Taiwan's energy policy objectives.
Compared to traditional boiler-based systems that directly burn fuel, the H-25 gas turbine improves plant efficiency and lowers CO2 emissions for cogeneration applications.
Chang Chun Petrochemical recently ordered one
Per the order, Mitsubishi Power will supply the primary gas turbine and auxiliary equipment, in addition to dispatching an engineering team to execute equipment installation and commissioning. In 2023, the company obtained an H-25 gas turbine order for the Miaoli Factory, with operation scheduled in summer 2026. This new order marks the second H-25 unit to be installed at the same factory.
This installation aligns with Taiwan’s energy policy objectives, as the H-25 gas turbine improves cogeneration plant efficiency and reduces CO2 emissions compared to traditional boiler-based systems that directly burn fuel. The H-25 gas turbine also demonstrated significant reliability across extensive long-term operational experience. Since the first unit order in 1987, Mitsubishi Power has supplied and operated over 200 H-25 turbines globally.
Since 1984, Mitsubishi Power delivered key equipment for power generation and cogeneration facilities at Chang Chun Group factories, including nine steam turbines and five boilers. The company still provides after-sales services and numerous solution offerings for Chang Chun. This recent order reflects the track record and long-standing relationship between Mitsubishi Power and Chang Chun Petrochemical.
Tung Hsiao Power Plant
In September 2025, the Taiwan Power Co. granted Mitsubishi Power and CTCI Corp. a $5.2 billion contract to execute a full turnkey project at its 2,800-MW
The five new turbine units will begin operation sequentially from 2030 to 2031, with generators supplied by Mitsubishi Generator Co. Several GTCC power plants, updated in the renewal’s first phase and located near the new facility, are equipped with three M501 JAC units operating since 2018. These units arrived following a joint contract awarded to Mitsubishi Power and CTCI in 2013.
Taiwan Power’s Tung Hsiao plant is located approximately 130 km southwest of Taipei and based on Taiwan’s long-term power supply and development plan, it will replace existing power plants once renewal work is completed. The renovation aims to increase power generation capacity and reduce environmental impact, while meeting the region’s rising industrial and residential electricity demand. In addition, the project also helps Taiwan in meeting its net-zero emissions goal.
Power in the Mekong Delta
In cooperation with Doosan Enerbility, Mitsubishi Power agreed to deliver two M701 JAC gas turbines and auxiliary equipment for Petrovietnam’s 1,155-MW
Newsletter
Power your knowledge with the latest in turbine technology, engineering advances, and energy solutions—subscribe to Turbomachinery International today.





