Siemens bags operation, maintenance contracts for 4.8 GW combined cycle in Egypt

Published on: 

The Egyptian Electricity Holding Co. chose Siemens to provide operation and maintenance services for the Beni Suef, New Capital and Burullus power plants, for the next eight years.

The agreement includes the implementation of the company's Omnivise digital service solutions.

The three 4.8 GW power plants represent about 40 percent of Egypt's power capacity, at the time of signing contracts, generating 14.4 GW – enough to supply 40 million Egyptians with electricity.

Advertisement

The multi-year agreement covers all on-site equipment including 24 gas turbines, twelve steam turbines, 36 generators, 24 heat recovery steam generators and three 500 kV gas-insulated switchgear systems.

Siemens will also implement its services portfolio to improve asset visibility, reliability and availability of the three power plants. Data from the plant operation will be collected, analyzed and transformed into actionable insights such as accurate diagnostics, troubleshooting and condition forecasting, improving plant reliability and reducing downtime. Additionally, the data processed can help to balance maintenance costs, optimize inspection intervals and provide valuable insights into operational risks.