Siemens Energy Closes Record Fiscal 2026 With €164 Billion Backlog as Gas Services Orders Climb 46%
Key Takeaways
- Gas Services orders rose 45.9% largely due to record 42 GW gas turbine unit orders and 104 GW in year-end commitments, including 39 GW of slot reservations poised to convert.
- Segment backlog climbed 35% to €74 billion, reflecting strong demand capture and improved execution, alongside a margin increase to 16.4% from 13% year-over-year.
Siemens Energy reported record fiscal 2026 orders of €68.1 billion, with Gas Services orders up 45.9% to €32.8 billion, and raised its 2030 margin target to 20% to 22%.
Siemens Energy announced that it ended fiscal 2026 with record orders of €68.1 billion, up 18.8% on a comparable basis, and a record order backlog of €164 billion.1 Comparable revenue rose 15.5% to €44.2 billion, and profit before special items more than doubled to €5.5 billion, a 12.4% margin.1
Why did Siemens Energy's Gas Services orders increase 46% in fiscal 2026?
Gas Services orders rose 45.9% to €32.8 billion, roughly half of group orders. Segment revenue was €14.5 billion, up 20.3%, and profit before special items was €2.4 billion, a 16.4% margin compared with 13% a year earlier.1, 2
On the earnings call, according to a transcript published by Investing.com, management put fiscal 2026 gas turbine unit orders at a record 42 GW and said year-end commitments reached 104 GW, made up of 65 GW of firm orders and 39 GW under slot reservation agreements. Management expects the reservations to convert to firm orders in fiscal 2027 at better margins than this year's orders. Gas Services backlog stood at €74 billion, up 35%.3 Siemens Energy also said its medium gas turbine capacity rose from about 50 to about 80 units a year, with large turbine capacity coming online from fiscal 2027, and that data center customers account for about €15 billion of the backlog, less than 10%.3
Group Results and Outlook
Grid Technologies orders rose 14.5% to €24.0 billion. Siemens Gamesa orders fell 31.1% to €5.9 billion against a strong prior year, but the wind unit reached break-even, with profit before special items of €8 million versus a €1.4 billion loss in fiscal 2025.1 Net income was just over €4.1 billion and pre-tax free cash flow was €8.8 billion. The company proposed a dividend of €2.30 per share, up from €0.70, and an additional buyback of up to €9 billion through the end of fiscal 2030.1
"We met all raised guidance targets, significantly increased earnings and achieved break-even in our wind business," said CEO Christian Bruch.1
For fiscal 2027, Siemens Energy expects comparable revenue growth of 14% to 16%, a profit margin before special items of 14% to 16%, net income of about €5 billion and pre-tax free cash flow of about €10 billion. By 2030, it targets 12% to 14% annual revenue growth and a 20% to 22% margin.1 GreentechLead reported that Gas Services guidance for fiscal 2027 is 24% to 26% comparable revenue growth and an 18% to 20% margin.2
What to Watch
Order growth slowed in the fourth quarter. According to the call transcript, group orders were €14.8 billion, up 5.2% comparable, and Gas Services booked about 2 GW, which management attributed mainly to timing.3 The third quarter was far stronger: Turbomachinery International
References
1. Siemens Energy reports record year and sets ambitious targets for 2030. Siemens Energy press release; Nov. 11, 2026. Accessed Nov. 13, 2026. https://www.siemens-energy.com/global/en/home/press-releases/siemens-energy-reports-record-year-and-sets-ambitious-targets-fo.html
2. Siemens Energy Revenue Jumps 15.5% to €44.2 Billion, Orders Hit €68.1 Billion, Backlog Reaches Record €164 Billion. GreentechLead; Nov. 11, 2026. Accessed Nov. 13, 2026. https://greentechlead.com/wind/siemens-energy-revenue-jumps-15-5-to-e44-2-billion-orders-hit-e68-1-billion-backlog-reaches-record-e164-billion-56470
3. Earnings call transcript: Siemens Energy shares jump on record Q4 2026 results. Investing.com; Nov. 11, 2026. Accessed Nov. 13, 2026. https://www.investing.com/news/transcripts/earnings-call-transcript-siemens-energy-shares-jump-on-record-q4-2026-results-93CH-5018439
4. Siemens Energy Posts Record Backlog, Joining GE Vernova and Baker Hughes in a Record Quarter for Gas Turbines. Turbomachinery International; Aug. 6, 2026. https://www.turbomachinerymag.com/view/siemens-energy-posts-record-backlog-joining-ge-vernova-and-baker-hughes-in-a-record-quarter-for-gas-turbines
5. GE Vernova's Gas Power Backlog and Reservations Reach 122 GW as Power Orders Jump 178%. Turbomachinery International; Oct. 29, 2026. https://www.turbomachinerymag.com/view/ge-vernova-q3-2026-gas-power-backlog-122-gw-trench-acquisition